Project:
Judicial Center Security Screen Improvements
Judicial Complex
43-47 High Street, Newton, NJ 07860
Designer:
Parette Somjen Architects
Contractor:
Zitone Construction and Supply Company, Inc.
Construction Schedule:
Bid Award Date: 1/28/2015
Project Start Date: N/A
Construction Completion Date: N/A
Construction Funding:
2011 County Capital - $14,460.00
2013 County Capital - $75,000.00
Construction Activities:
• Pre-Construction meeting to occur in the near future
• Construction Documents received from Parette Somjen Architects
• No bids were received on either bid dates of June 17, 2014 and August 8, 2014
• Approval for FMD to negotiate with Contractors outside of the bid process was approved at the 09/10/14 BCF Meeting