Cochran House HVAC Improvements
Updated: March 24, 2015
Project:
Cochran House HVAC Improvements
Cochran House Building
83 Spring Street, Newton, NJ
Designer:
LJM Engineering Group, Rockaway, NJ
Contractor:
AMCO Enterprises, Inc.
Construction Schedule:
Bid Award: 5/14/2014
Construction Start Date: 9/29/2014
Construction Completion Date: 2/25/2015
Construction Funding:
2011 County Capital - $346,724.21
Construction Activities:
• Testing and balancing of the system is completed
• Final walkthrough with LJM Engineering was performed on February 25, 2015