9-1-1 Emergency Communications Center Construction Update

Exterior of communications center
Floor plan of communications center

Updated: January 20, 2015

Project:

9-1-1 Emergency Communications Center

Office of Emergency Management
135 Morris Turnpike, Newton, NJ (Frankford Township)

Designer:

HQW Architects, LLC

Contractor:

Construction Schedule:

Bid Award: September 12, 2012
Project Start Date: September 13, 2012
Construction Completion Date: December 16, 2014

Construction Funding:

$1,147,219.00

2011 County Capital - $400,000.00
2012 County Capital - $747,219.00

Construction Activities:

• Construction Documents received from HQW Architects
• Pre-Construction Conference held on September 24, 2012.
• Remainder of work was completed using County staff and selected vendors
• A settlement was reached with Tekton Development Corp. on November 15, 2013, removing them from the remainder of the project